1 Megawatt Cooling for Rolling Mill Emergency
case studies
Another Project
- 1 megawatt contort cooling
- 50kw process cooling
- 60kw factory cooling
- 200kw factory cooling
- 800kw process cooling
Check On Our Linkedin Post
The Challenge
Production Disruption in Steel Rolling Operations
The call came through on a Tuesday afternoon. A steel processing facility running continuous rolling mill operations had lost its primary process cooling system. The plant’s dedicated chiller train, which had been keeping coolant temperatures stable between 12°C and 16°C across the mill stands, had failed at the compressor stage. The backup unit, which had never been properly commissioned, wouldn’t start.
Without industrial temperature control, the rolling mill was running hot. Bearing housings were climbing toward thermal trip thresholds. The production floor had roughly four hours before they’d be forced into a full shutdown — and with a live order schedule and penalty clauses in play, that was not an option the operations director was willing to accept.
What the site needed was immediate 1MW cooling capacity — the full thermal load of the mill at production rate. A fully deployed temporary cooling solution was required immediately.
The Survey
Full Thermal Load & Site Assessment
A Rapid Chillers engineer was on site within three hours. The survey was a full technical assessment covering:
– Pipework configuration across all cooling circuits
– Electrical and power supply infrastructure
– Thermal load analysis per system loop
– Site access constraints and 40m pipework routing
– Integration points into existing distribution headers
The site ran three distinct cooling loops: roll cooling headers, hydraulic system heat exchangers, and motor cooling circuits. Each had different flow and temperature requirements.
Total confirmed heat rejection: ~980kW, requiring 1MW continuous cooling capacity.
The Solution
1MW Temporary Chiller Package Deployment
Rapid Chillers mobilised a 1000kW chiller package (1MW total capacity) by deploying two containerised industrial chillers from the hire fleet, each rated at 500kW, configured in parallel to deliver the required cooling capacity as a matched pair. Both units were air-cooled and self-contained — no cooling tower, no additional infrastructure, no delay waiting on civils.
Hoses and flow control valves were dressed to the site’s existing headers overnight. The plant’s electrical team handled the power connection under Rapid Chillers’ supervision, with both units energised and brought up to operating setpoint before the morning shift. By 06:30, supply water temperature was stable at 14°C across all three circuits — exactly where the mill needed it.
The system was integrated into the existing cooling architecture with full remote monitoring and 24/7 operational support throughout the hire period.
The Result
Zero Production Loss & Full System Recovery
The rolling mill resumed full production the morning after the cooling failure. Total unplanned downtime: eleven hours, including the time before Rapid Chillers was engaged. The temporary 1 megawatt cooling package ran continuously for six weeks while the site’s permanent chiller was stripped, rebuilt, and recommissioned by their OEM.
Throughout that period, coolant supply temperatures held within ±0.5°C of setpoint. There were no thermal trips, no bearing overtemps, no interruption to the production schedule. The operations director later confirmed that the order penalties they’d been facing were avoided entirely.
Industrial chiller hire at 1MW scale requires rapid mobilisation, proven expertise, and reliable integration under live production conditions. Rapid Chillers delivers all three, even in critical failure scenarios. Process cooling failure in heavy industry is rarely clean or simple. What matters is how fast the right equipment gets to site, and whether the team commissioning it understands the process it’s protecting.
For contract cooling requirements across rolling, extrusion, or any continuous industrial process, contact Rapid Chillers.
Related Projects

Portable Air - Conditioning
This project was a challenge, we had a good power supply but no opening windows to discharge the waste heat, we needed to get creative! if we were going to help. We achieved this by installing ducting that vented directly into the air extract, the fix is crude but allowed installation of 5 of our 7.3KW portable coolers that reduced the room temperature by an impressive 11 degrees.

Bakery Chiller Breakdown
Following a call from a local site engineering manager, to advise his chiller had tripped in the summer heat we rushed to help. On site in less than 30 minutes, our sales manager got our lead engineer on the phone who talked the site's services engineer through the chiller checklist and restart. No hire service was provided but the client, realising they were vunerable asked for a chiller contingency plan to be created, so the site is better prepared to cope if there isnt a fix in the future.

NHS Hospital
The client called us after finding our website on the internet. They needed three chillers servicing, we don't offer this service but we do have a good network of air-conditioning and industrial refrigeration contractors that provide the required service. We referred the caller to a local service partner who has quoted and secured the service contract. Another example of how we're prepared to go the extra mile to aid you finding the right solution.