800kW Process Cooling for Chemical Production Plant Failure
case studies
Another Project
- 1 megawatt contort cooling
- 50kw process cooling
- 60kw factory cooling
- 200kw factory cooling
- 800kw process cooling
Check On Our Linkedin Post
The Challenge
A critical cooling failure at a chemical production plant put continuous operations at risk. The site depended on a tightly controlled chemical plant cooling system to regulate temperatures across multiple reaction vessels. When the primary process chiller unit failed unexpectedly, temperatures began to rise within hours.
This wasn’t a situation where production could simply pause. The plant was running heat-sensitive processes that required stable cooling to prevent batch loss and safety concerns. Without immediate industrial process cooling, the site faced halted production, wasted materials, and contractual penalties.
Their internal team identified the issue quickly, but sourcing replacement parts for the existing system would take weeks. What they needed was an emergency cooling solution—fast, reliable, and capable of delivering the full required cooling capacity kW without disrupting the existing setup.
The Survey
Rapid Chillers responded immediately, dispatching an engineer to site the same day. The survey focused on more than just replacing lost capacity—it was about understanding how cooling was distributed across the plant and how best to restore it without interruption.
A full assessment of the heat rejection system was carried out, including flow rates, temperature setpoints, and load across each process line. The plant required close to 800kW process cooling, which would be delivered using a high-capacity 800kW chiller to maintain stable operation under peak conditions.
The engineer also evaluated physical constraints. Space for equipment placement was limited, and pipework connections needed to align with the existing chilled water system. Power availability, access routes, and safe installation of temporary pipework were all factored into the plan.
The Solution
Rapid Chillers mobilised a high-capacity 800kW process cooling package from its chiller rental UK fleet. The system included an air-cooled industrial chiller, supported by a pump set and buffer tank to maintain consistent flow and temperature control.
The equipment was pre-configured off-site to match the plant’s operating conditions, reducing installation time once on location. Temporary pipework was installed to connect directly into the plant’s existing distribution headers, allowing seamless integration with the current chemical plant cooling system.
Delivery, installation, and commissioning were completed within 48 hours. The system stabilised temperatures quickly, restoring full control across all production processes.
Throughout the hire period, the industrial chiller hire setup was monitored to ensure consistent performance under continuous load.
The Result
Production continued without interruption. The 800kW process cooling system maintained stable temperatures within required tolerances, preventing batch loss and protecting product quality.
The plant avoided costly downtime and maintained its production schedule despite the critical cooling failure. Engineers were able to repair the original system without pressure, knowing a reliable temporary solution was in place.
The success of the project reinforced the value of having access to rapid-response industrial process cooling support. For the client, it wasn’t just about replacing cooling—it was about keeping the entire operation running when it mattered most.
Related Projects

Portable Air - Conditioning
This project was a challenge, we had a good power supply but no opening windows to discharge the waste heat, we needed to get creative! if we were going to help. We achieved this by installing ducting that vented directly into the air extract, the fix is crude but allowed installation of 5 of our 7.3KW portable coolers that reduced the room temperature by an impressive 11 degrees.

Bakery Chiller Breakdown
Following a call from a local site engineering manager, to advise his chiller had tripped in the summer heat we rushed to help. On site in less than 30 minutes, our sales manager got our lead engineer on the phone who talked the site's services engineer through the chiller checklist and restart. No hire service was provided but the client, realising they were vunerable asked for a chiller contingency plan to be created, so the site is better prepared to cope if there isnt a fix in the future.

NHS Hospital
The client called us after finding our website on the internet. They needed three chillers servicing, we don't offer this service but we do have a good network of air-conditioning and industrial refrigeration contractors that provide the required service. We referred the caller to a local service partner who has quoted and secured the service contract. Another example of how we're prepared to go the extra mile to aid you finding the right solution.